Event | Time [min:sec] |
Liftoff | 00:00 |
SSB ignition | 00:10 |
SSB jettison | 01:30 |
SRB-A jettison | 02:05 |
Payload fairing jettison | 04:25 |
1st/2nd stages separation | 06:48 |
2nd stage engine 1st ignition | 06:54 |
2nd stage engine 1st cutoff | 12:07 |
2nd stage engine 2nd ignition | 40:33 |
2nd stage engine 2nd cutoff | 44:02 |
Satellite separation | 45:32 |
(Note) The H-IIA F13 mission aims to inject its payload into the lunar transfer orbit, and the length of the coast flight phase varies depending on the launch day. This chart shows a flight case with the longest coast phase as a typical example.